08 Timeline
Eleven months, five phases, one campus on the other side.
A practical sequence that keeps the property running while the work happens.
1
Validation
Now – 30 days
· Confirm utility baseline
· Roof inspection
· SCE pre-application
2
Engineering
30 – 90 days
· Stamped structural
· Electrical SLD
· Permit submittals
3
Procurement
60 – 150 days
· EPC contract
· Carport order
· EV charger order
4
Construction
150 – 270 days
· Trenching
· Service upgrade
· Solar install
· Carport build
5
Closeout
270 – 330 days
· PTO from SCE
· Direct Pay filing
· Commissioning report