08 Timeline

Eleven months, five phases, one campus on the other side.

A practical sequence that keeps the property running while the work happens.

  1. 1

    Validation

    Now – 30 days
    • · Confirm utility baseline
    • · Roof inspection
    • · SCE pre-application
  2. 2

    Engineering

    30 – 90 days
    • · Stamped structural
    • · Electrical SLD
    • · Permit submittals
  3. 3

    Procurement

    60 – 150 days
    • · EPC contract
    • · Carport order
    • · EV charger order
  4. 4

    Construction

    150 – 270 days
    • · Trenching
    • · Service upgrade
    • · Solar install
    • · Carport build
  5. 5

    Closeout

    270 – 330 days
    • · PTO from SCE
    • · Direct Pay filing
    • · Commissioning report